Why Occupation Certificates get delayed, and how to avoid it

An Occupation Certificate allows a new building, or part of one, to be occupied and used. It can also be needed before starting a new use of an existing building. Delays at this stage often come down to paperwork, and many can be avoided with some planning.
Common causes
- A critical stage inspection was missed during the build
- A trade certificate is missing. Depending on the work, examples include waterproofing, glazing, electrical, and plumbing and drainage
- BASIX commitments have not been completed or cannot be shown
- The finished work differs from the approved plans
- Conditions of the development consent or CDC have not been met
- For buildings that need one, the fire safety certificate has not been provided
- The OC application has not been lodged on the NSW Planning Portal
Certifier’s note
Ask for the OC checklist when the frame goes up, not when the painters leave. Collect each certificate as the trade finishes, while they are still on site and easy to reach.
How to avoid them
- Keep a folder of certificates from the start of the job
- Tell your certifier about any design change before it is built. Some changes need a modified approval
- Book the final inspection ahead of time, and have the work finished and the documents ready before the day
- Lodge the OC application on the NSW Planning Portal early
Using part of a building early
For consents granted from 1 December 2019, interim and final occupation certificates no longer exist. An Occupation Certificate can cover the whole building or an identified part of it, provided the requirements for that part are met and it is safe to occupy. If an OC is issued for the first completed stage of a partly finished building, an OC for the whole building must be obtained within five years. Agree the staging with your principal certifier before you plan a move-in date.