Certifiers reviewing a part-built home after taking over as principal certifier

If your principal certifier is not responding, has stopped practising or is simply not the right fit, they can be replaced part-way through a build. The change is made by the person entitled to appoint the principal certifier, which is usually the property owner. A builder cannot make that choice for you, unless the builder also owns the land, for example an owner-builder.

Option 1: by agreement

The quickest way is for you, your current certifier and the replacement certifier to all agree and sign the replacement notice. Building Commission NSW advises telling the council, or the consent authority if that is someone else, before the appointment is made. The incoming certifier then lodges the notice on the NSW Planning Portal and notifies the consent authority and the council within two days of being appointed.

Option 2: by application to Building Commission NSW

If agreement cannot be reached, or your certifier’s registration has expired or been suspended or cancelled, you apply to Building Commission NSW. Written approval is needed, and the council and consent authority must be notified, before the replacement happens. Building Commission NSW also asks applicants to notify the former certifier.

You need to give good reasons, with the relevant events and dates. Building Commission NSW says assessment takes six to eight weeks on average.

Certifier’s note

Try for agreement first. It avoids a wait of several weeks while an application is assessed.

What the new certifier will need

  • The development consent or CDC, with stamped plans
  • The Construction Certificate, if there is one
  • The original notice appointing the principal certifier
  • Records of the inspections already carried out
  • Engineer’s and trade certificates issued so far
  • Planning Portal application numbers

Missed inspections

Changing certifiers does not reset the inspection history. A new certifier cannot go back and inspect work that is already covered, and a missed inspection is not automatically fixed by the change. Ask the incoming certifier early about any gaps in the inspection history and what it may take to resolve them, so there are no surprises at Occupation Certificate stage.