Approvals · 6 min read
CDC or DA? How to choose the right approval pathway for your NSW project

Complying development can turn a months-long approval into a much shorter one. But only if your site and design qualify, and that is worth confirming before you commit to full drawings.
What’s the difference?
A Development Application (DA) is assessed on its merits by the consent authority, which is usually your council. The proposal is weighed against the planning controls and can be approved, refused or approved with conditions. Whether a DA is publicly exhibited or neighbours are notified depends on the type of development. Since 1 September 2026 a single statewide Community Participation Plan sets those rules, and some lower-impact development is no longer exhibited. Once you have consent, you generally still need a Construction Certificate before you can build.
A Complying Development Certificate (CDC) combines planning and construction approval in one. If your project meets the set standards in the relevant State Environmental Planning Policy, a council or a registered certifier can approve it without a merit assessment.
When CDC is usually possible
- New one or two storey homes on standard residential lots
- Alterations and additions that meet setback, height and site coverage limits
- Granny flats (secondary dwellings) on qualifying lots
- Swimming pools, decks and outbuildings
Certifier’s note
Common reasons a CDC cannot be issued include a site constraint found late, such as a heritage listing, a flood control lot or a high bushfire rating. Check these before you lodge, not after.
When you’ll need a DA
Heritage items, land in certain flood or bushfire categories, environmentally sensitive land and designs that exceed the numeric standards generally need a DA. Heritage is not all-or-nothing: some minor work in a heritage conservation area can still be complying development. A DA also gives more design flexibility where your site is irregular.
How to decide
Start with a section 10.7 planning certificate for the lot. It is a screening tool, not the final answer. The design still has to be checked against the applicable code, maps and development standards. Depending on the land, a survey, flood information or a bushfire assessment may be needed before CDC eligibility can be confirmed.
Before work starts
With either pathway, a principal certifier must be appointed and the required notices given before work begins. For some CDCs, neighbours must be given notice before the certificate is issued, so allow for that in your program.